BRIFEN

WIRE ROPE SAFETY FENCE

TYPICAL SITE INSTALLATION PROCEDURES

1. All the ropes are supplied on wooden reels. The two lower ropes are always slightly longer to allow for the inter-weaving between the barrier posts. The ropes are specially cut to length and wound on to the reel in such a way that when the ropes are run out on site they should line up exactly with the anchorage positions.

2. The first step in installing the barrier is to insert a steel post, complete with Z washer dirt excluder, into each of the concrete sockets. Standard Drawings show where the deflection posts (the ones with the welded lugs on each side) are positioned at each anchorage.

3. The black plastic pegs must then be inserted into the posts. It is better to fit the plastic pegs at this stage rather than trying to fit them before the posts are delivered to site. This is because it is difficult to stack the posts once the pegs are inserted.

4. The two lower ropes must always be installed first since they interweave between the posts. The lower ropes are the first to come off the reel, then the upper ropes. The reel should be mounted on a reel stand on the back of a truck or trailer. It is better if the reel stand does not have bearings. This ensures that the rope remains reasonably taut while it is being run off.

5. It does not matter which end of the barrier is used as the start point for running out the ropes. However, all the ropes should be run out from the same end. This will ensure that the rigging screws are kept away from the area close to the post.

6. Begin running out the first rope by connecting it into the end anchor as follows. Fit a safety check rope over the end of the rope and then fit a square polyethylene insert, steel backing plate and two nuts (or the mechanical fitting). Only screw on the nuts until a full thread has been obtained. Insert the rope into one of the slots in the outermost end anchor, so that the polyethylene insert is sandwiched between the steel backing plate and the anchor. Please see the Standard Drawings for the correct assembly of the anchor fittings. (Drawing No. LB/128).

7. Drive slowly alongside the barrier posts reeling off the rope. Another person walking behind the truck should weave the rope between the posts, resting it on the plastic pegs. When the end of the rope is reached it will be found that the next rope is tied to the end with twine. After cutting away the twine the two ropes are connected together using a rigging screw. At this stage, only engage approx. 25mm thread, leaving the remaining thread for tensioning when all the ropes have been run out. As mentioned before, provided that the reel stand does not have any bearings, there will be sufficient friction on the reel stand to keep the rope reasonably taut.

8. When the end anchor is reached, the rope is connected as follows. Having started running out from the outermost anchor, the ropes now terminate at the innermost anchor. It will be found that there is approximately two metres of surplus rope, and there is no threaded fitting swaged on the end. Fit a safety check rope, a square polyethylene insert, steel backing plate and then attach one of the mechanical anchor fittings over the end of the rope.

A lever hoist should now be used to pull through any slack. It can be attached to the rope by a clamp (available from LB Wire Ropes), and anchored to the bottom of a Brifen post. The rope is then positioned in one of the slots in the anchor frame so that the polyethylene insert is sandwiched between the steel backing plate and the anchor. Ensuring that the mechanical anchor fitting is gripping the rope, the lever hoist can then be removed and the excess rope can be cut off.

Care must always be taken using a lever hoist to ensure that it is securely connected. If either attachment slips off while under tension it can result in serious injury to the operator, or person nearby.

9. Take the truck/trailer containing the reel stand back to the original start point. Running out the second of the lower ropes is largely a repeat of the above procedures. However, this time, the lower rope starts from the innermost of the pair of end anchors and finishes at the outermost end anchor.

10. The installation of the upper ropes is basically a repeat of the procedures used for the lower ropes. The main difference is that the upper ropes do not interweave between the barrier posts, but are positioned in the slots in the tops of the barrier posts.

11. The first of the upper ropes should start from the outermost of the pair of end anchors and will terminate at the innermost of the pair of end anchorages. The second upper rope starts from the innermost end anchor and terminates at the outermost end anchor.

12. The slack in the ropes should be gradually taken out by tightening up each of the rigging screws in turn. This should be done in stages so that the slack is taken up evenly along the full length of the barrier, and ensuring that each of the threads engaged in the rigging screws has at least 50mm of engagement. Also ensure at every anchor that the rope fittings are pressed down in the anchor slots.

13. Using the tension meter, which can be quickly attached to the rope, continue to tighten the rigging screws progressively along the full length of the barrier to increase the tension in the ropes. It is recommended that this be done in stages, building up to the required tension. The final tension will be determined by the ambient temperature conditions, using the chart supplied by LB Wire Ropes.

14. The plastic caps and reflectors can now be fitted to every post.

15. Ensure that all of the safety check ropes are securely attached to the anchor frames using the clevis fitting which is swaged onto the end of the safety check rope.

16. When tensioning is completed the swaged fittings on the ends of every rope and the mechanical anchor fittings should be wrapped in "Denso tape" or equivalent, or should be given a coating of waterproof grease. This is to ensure that the threads remain free from corrosion, thus enabling any re-tensioning to be easily performed in future years.



HOME PAGE Selection Criteria
Specifications Standards
Performance History Testing to International Standards
Barrier Maintenance Installations in Australia
Reference Photographs Standard Drawings
Reference Articles Typical Procedures for Concrete Foundations

 

 
   



Link to Spec-Net Building Index